Home / Capabilities / Interconnection

The bore between completion and energization

Gen-tie and interconnection drilling that carries collected power from the array into the point of interconnection, substation, or switchyard. The last underground scope your COD depends on.

The interconnection bore carries the gen-tie circuit from the array into the point of interconnection, POI, substation, or switchyard. It is the conductor path that lets a finished field actually backfeed the grid. Because it sits between mechanical completion and energization, it is the single bore most likely to move commercial operation if it slips. We drill it on the critical path and treat the schedule as the deliverable.

500K+
Feet bored
100+
Bores on schedule
12
Solar fields
0.86
EMR safety
// THE CRITICAL-PATH BORE

From the array to the point of interconnection

Every collected feeder on a utility-scale field funnels toward one place: the gen-tie that ties the project into the grid. That gen-tie has to leave the array, cross whatever sits between the last collection point and the POI, and land inside the substation or switchyard. Almost all of that path is underground, and the hardest segments are bored, not trenched. We drill the gen-tie and interconnection crossings so the conductor arrives at the point of interconnection ready to terminate.

This is not a generic utility bore. It is the conductor that decides whether a mechanically complete field can energize. We plan it as the last thing standing between the project and commercial operation, and we sequence everything around that fact.

Why this is the highest-stakes bore on the project

On a solar build the schedule funnels into a single chokepoint at the end: energization. Modules can be set, racking torqued, inverters landed, and the field still cannot produce a kilowatt-hour until the gen-tie is in the ground, terminated, and the utility energizes the point of interconnection. The interconnection bore sits squarely in that gap.

  • It is downstream of everything. Mechanical completion does not earn revenue. Energization does. The gen-tie is the last conductor between the two.
  • It is on a hard date. Utility energization and witness-test windows are scheduled months out and do not move easily. Miss the bore and you miss the window, then you wait for the next one.
  • It crosses the worst ground last. The approach to a POI often runs under a highway, a rail spur, or a waterway, the crossings that gate energization and carry the most permit and frac-out risk.
  • It is shared scope. The bore, the switchyard buildout, and the utility's work all converge at the fence line. Any one of them can stall the others.
The bore is on the critical path. We make sure it never holds up your COD.

The last crossings before the POI

The crossings that gate energization are almost always the ones closest to the point of interconnection: a state highway, a rail line, a stream or wetland, or a corridor of existing utilities on the substation approach. These are the bores that have to be permitted, drilled, and proven before the gen-tie can land. We treat them as energization-gating work from day one.

  • Highway and road crossings at the depth, casing, and bore geometry the DOT or crossing owner requires, with permit-ready profiles.
  • Rail crossings drilled to the railroad's cover and encasement spec, sequenced around flagging and track-access windows.
  • River, stream, and wetland crossings drilled with a written inadvertent-return plan, drilling-fluid program, and containment so a sensitive crossing does not become a permit problem.
  • Existing-utility crossings located by vacuum excavation and potholing before we drill, so the gen-tie threads the corridor cleanly. See our vacuum excavation and SUE scope.

Coordination at the fence line

The interconnection scope is where the most parties meet on a solar project, and coordination failures here cost energization windows. We sequence our work against everyone who touches the POI.

  • The utility or transmission owner sets the energization date, the witness-test requirements, and what has to be complete and inspected before they backfeed, under the generator interconnection procedures the project is studied against.
  • The switchyard or substation contractor owns the getaway and the terminations. We hand off a clean, located, as-built conduit path at the fence so they can pull and land circuits without surprises.
  • The EPC and GC schedulers get a bore plan with real durations, hold points, and a contingency line so the interconnection scope shows up correctly on their critical path.
  • The inspector or authority having jurisdiction sees a documented bore, a depth-of-cover record, and an as-built that supports sign-off without a re-dig.

Conduit and duct bank at the substation getaway

The gen-tie does not just need a bore. It needs a finished, testable path into the substation. We carry the work from open ground to the getaway and hand off a circuit ready to terminate.

  • Bore-to-duct-bank transition at the substation approach, tied into the getaway structure the switchyard contractor is building.
  • Conduit and duct bank for the gen-tie circuits, plus any fiber, SCADA, or protection-and-control pathways routed alongside.
  • Mandrel and proof testing on every conduit so the pull path is verified before anyone shows up to pull conductor.
  • As-built handoff with depth-of-cover, alignment, and conduit counts documented for the utility and the AHJ.

Schedule certainty, in writing

Because this bore decides energization, we de-risk it on paper before a rig moves. Every interconnection crossing ships with a geotech read, a drilling-fluid and inadvertent-return plan, a monitoring and containment scheme, and a written contingency. The point is simple: the interconnection bore is the one piece of underground scope that can move your COD, so it is the one we plan in the most detail. Pair it with our 34.5kV collection scope and the entire conductor path, from feeder to POI, comes from one crew.

// ONE CREW TO THE POI

Collection and gen-tie from one accountable crew

When the same owner-operated crew drills the 34.5kV collection and the interconnection bore, the conductor path has one owner from the array to the point of interconnection. No handoff seam between feeder and gen-tie, no finger-pointing if the energization window gets tight. One bore plan, one as-built, one schedule line.

We run owner-operated rigs and crews, not a single financed drill chasing the next job. That means the people who planned your interconnection bore are the people in the seat when it matters.

HDD rig and crew positioned for a gen-tie bore on the approach to a substation getaway
// FIELD WORK

Interconnection scope in the field

HDD rig set up for a gen-tie crossing toward the point of interconnection Crew staging conduit and duct bank at a substation getaway Directional drilling equipment on a utility-scale solar interconnection bore
// FAQ

Interconnection bore FAQ

Why is the interconnection bore the highest-stakes crossing on a solar project?

It sits directly between mechanical completion and energization. Until the gen-tie is in the ground and terminated into the point of interconnection, the field cannot backfeed and the project cannot reach commercial operation. A slipped interconnection bore moves COD, not just a milestone.

Who do you coordinate with on the interconnection scope?

The utility or transmission owner, the switchyard or substation contractor, the EPC and GC schedulers, and the authority having jurisdiction or inspector. We sequence the bore, the getaway conduit, and the as-built around their energization and inspection windows so nothing waits on us.

Can you handle the conduit and duct bank at the substation getaway?

Yes. We pull the gen-tie circuits and any fiber or SCADA into the substation getaway, transition from bore to duct bank, and hand off a clean, mandrel-tested, as-built path at the fence line for the switchyard contractor to terminate.

What about the last crossings before the POI, like a highway or rail?

Those are usually the bores that gate energization. We carry the gen-tie under highways, rail, and water on the approach to the point of interconnection with a written inadvertent-return plan, permit-ready geometry, and the depth and casing the crossing owner requires.

// STANDARDS & REFERENCES

Standards and references

The gen-tie and interconnection scope is planned and sequenced around the interconnection, energization, and substation standards the industry relies on. Useful references:

  • FERC — Generator Interconnection — the federal procedures and agreements that govern how a generating facility studies, schedules, and reaches energization at the point of interconnection.
  • IEEE 1547 — the standard for interconnection and interoperability of distributed energy resources with the electric power system that the interconnection terminations are designed to meet.
  • IEEE Standards Association — publisher of the National Electrical Safety Code (NESC) and related standards that govern substation getaway and switchyard work the gen-tie hands off into.
// DON'T LET THE BORE GATE YOUR COD

Lock the bore that energizes the field

Send us the gen-tie alignment, the crossings before the POI, and your energization date. We will scope the interconnection bore, the getaway conduit, and the schedule it has to hit.

Request capabilities